CyrusOne

City: 
Houston, TX

In an effort to respond to a large anchor Client-user, CyrusOne contracted NOVA to carry out a Critical Power and Mechanical systems upgrade, within a live Data Center.  This effort entailed the usage of temporary plant to carry the existing load while Chiller Units and UPS systems were upgraded to take the existing space from 200W/sqft to over 400W/sqft.

NOVA delivered this phase in less than 20 weeks, all working in and around live equipment. This allowed the internal Client to immediately begin integrating higher density IT equipment.