Equinix

City: 
Chicago, IL
Size: 
280,000 sqft

Located near O’Hare Int’l Airport, in a suburb about 20 miles west of Chicago, this Data Center facility boasts tight security features, redundant generators, ultra-modern functional interior and enormous mechanical rooms.

Structured as an upside down Data Center, the facility is approximately 280,000 sqft, currently housing a 50,000 sqft Data Center with room for future expansion. NOVA completed this greenfield project in a rapid 14-month delivery.

Further Project Data:

  • NOVA selected to provide in-depth Cost Analysis and Value Engineering
  • Original project estimate exceeded Client budget by $30 Million
  • NOVA successfully delivered the project for $33 Million less than original project estimate
  • Delivered the 280,000 sqft, 3-story Data Center in 14 Months