IBM required a complete replacement of the HV Switchgear at their North Harbour facility to minimize the risk to the Client’s existing electrical distribution to IBM and IBM Clients already occupying the live Data Center facility. NOVA was contracted to provide a turnkey delivery in pre-construction services, working with the Architect/Engineering teams to ensure proper and timely delivery, as well as commissioning assistance.

Further Project Data:

  • NOVA selected as Design/Build Construction Manager
  • Assist IBM and Architect/Engineer in reviewing the requirements of building codes and any other agencies having jurisdiction, advise on the cost impact of these requirements, and suggest possible alternates.
  • Provide pre-construction services to the future facility
  • Provide commissioning assistance of upgraded switchgear